LNG Main Boiler Retubing
- Source:
- Time of issue:2023-06-28 12:04
- Views:
(Summary description)
LNG Main Boiler Retubing
(Summary description)
- Categories:Company News
- Author:Alex Zhang
- Source:
- Time of issue:2023-06-28 12:04
- Views:
Two units of Mitsubish MB3E
Part I—Description of scope of work
Part II—Fabrication in workshop
Part III—Retubing on site
Part I—Description of scope of work
Background
Boilerman was requested to carry out complete retubing of two units of Mitsubishi MB3E type boilers in HRDD in Shanghai.
The retubing was confirmed in mid of March while job needed to be started in the beginning of April and completed within 70days.
All the materials incl. super heater tubes and supports were sourced locally in China and fabricated in Boilerman Shanghai workshop.
With the great support from HRDD, ship owner and management company, the job was completed within 70days as per the agreement and to the client and LRs satsifactory.
Scope of work:
- Complete renewal of front and rear wall tubes *2boilers
- Complete renewal of generating tubes *2boilers
- Complete renewal of superheater tubes *2boilers
- Complete renewal of superheater support tubes *2boilers
- Complete renewal of screen wall tubes *2boilers
- Complete renewal of floor, side, roof wall tubes *2boilers
- Complete renewal of de-superheater and control de-superheater*2boilers
- All Burner tiles, insulation, refractory *2boilers
Part II—Fabrication in Workshop
The fabrication of the material was carried out in parallel with the retubing work on site. Sample tubes were cut out and sent to the workshop for bending, swaging, making panels, assembling, NDT, pre-hydro test, etc.
Some sample tubes cutting from the boiler--Generating tubes, Manhole tubes, De-Superheater coils
Fabrication of the tubes in workshop
Fabrication of Superheater Panels
Part II—Retubing on site
As the job was confirmed in short notice, a mixed team with one British Project Manager, one Indian Supervisor, four Chinese Supervisor and forty+ people (Chinese, Indian, Pilipino) were gathered together for the site repair. A daily report as well as a progress S curve was reported to the client at the end of day shift.
Remove insulation and cladding | Remove furnace floor refractory | Remove superheater floor refractory |
Cropping out the tubes | Cropping out the tubes | Cropping out the tubes |
*Sufficient support tubes to be left to make sure headers and drum not sagging down
Splitting of tube ends | Removal of tube ends |
Grinding/Polishing tube holes | Removal of weldings at SH tube ends | SH tube ends punched out |
NDT (PT) on tube holes
Install and weld of the front/rear enclosure tubes
Install and weld of the front/rear wall tubes
Install and expand the generating tubes
Install and expand the superheater support tubes | Install and weld the screen wall tubes |
Install and weld the superheater tubes
Install and weld/expand the floor, side, roof wall tubes
Butt joint welding and X ray | Welding all the fins/flat bars |
Closing the boiler for hydro test
Hydro test of both boilers
Install the new DSH/CDSH and hydro test
Install the refractory in way of repair
Install the insulation, cladding and manhole covers